Bridge
BIN 106531K
NY27 WB to I278 EB over RAMP TO HAMILTON
GoodNYSDOT rating 5.45 of 7Inspected Jun 3, 20261 planned project
Planned and programmed work plans as published, not awarded contracts
- Painting of the Gowanus Expressway Viaduct between the Verrazzano-Narrows Bridge and the Hugh Carey Tunnel. The work consists of painting and steel repairs to prolong the useful life of the bridge. BINs include:1065318, 106531A, 106531B, 106531C, 106531D, 106531E, 106531F, 106531G, 106531H, 106531I, 106531J, 106531K, 106531L, 106531M, 106531N, 106531O, 106531P, 106531Q, 1075060, 1076740, 1076750, 1076849, 1076851, 1076852, 1074010.BRIDGE PRESERVATION · Contract D264703 · Planned completion Jan 3, 2026
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026; NYSDOT Capital Program projects. Our copy checked Nov 2, 2026.
Inventory facts
Location
- Carries
- NY27 WB to I278 EB
- Crosses
- RAMP TO HAMILTON
- County
- KINGS
- NYSDOT region
- (11) New York City
- Place
- New York (City)
- Location note
- JCT PROSPECT EXPY & I278
Ownership
- Owner
- NYSDOT
- Maintained by
- State - Subcontracted to another Party
Design
- Year built
- 1997
- Structure type
- 02 - Stringer/Multi-Beam or Girder
- Material
- 3 - Steel
- Spans
- 3
- Length (ft)
- 237
- Deck area (sq ft)
- 8840
Condition
- NYSDOT condition rating
- 5.451 (poor) to 7 (new)
- FHWA condition
- Good
- Poor status
- NoBridge Conditions dataset
- NBI superstructure
- 70 to 9
- Last inspection
- 2026-06-03
- Last inspection (Bridge Conditions)
- 2024-06-04
Load and traffic
- R-posted
- NOPosting flag as recorded
- AADT
- 15684Count year not supplied by this layer
Source: NYSDOT Bridges; Bridge Conditions, NYS Department of Transportation, updated Oct 5, 2026. Our copy checked Nov 2, 2026.
Contracts that name this BIN 0 in the record-plan index
No indexed contracts.
Source: NYSDOT Highway Record Plans, updated Jun 26, 2026. Our copy checked Nov 2, 2026. A BIN named in a contract's index row does not prove every drawing applies to this structure.