Project

PIN 204603

2023 CRP: SR 921B/BURRSTONE RD PED CONNECTIVITY PROJ, UTICA

Statewide Transportation Improvement Program programmed, not awarded

THIS PROJECT WILL ADDRESS SIDEWALK GAPS AND POOR SIDEWALK CONDITIONS BY CONSTRUCTING/RECONSTRUCTING SIDEWALK ON BOTH THE NORTH AND SOUTH SIDES OF BURRSTONE ROAD (NYS 921B), WEST OF FRENCH ROAD TO MARAUDER BOULEVARD IN THE TOWN OF NEW HARTFORD AND VILLAGE OF NEW YORK MILLS. THE BENEFICIAL OUTCOMES OF THIS PROJECT WILL INCLUDE PROVIDING RESIDENTS/PEDESTRIANS WITH A SAFE, CONTIGUOUS, NON-VEHICULAR, ADA COMPLIANT CONNECTION TO TRANSIT STOPS, HEALTHCARE FACILITIES, RESTAURANTS, EDUCATIONAL AND RELIGIOUS INSTITUTIONS.

Programmed
FFY 2026: $151k, FFY 2027: $1.5MTotal $1.7M in the listed years
Federal share
$1.3M
Agency
NYSDOT
Planning organization
HOCTC
County
Oneida
Fund types
CRP FLEX, CRP MED URB, SDF
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Oct 31, 2026. FFY is the federal fiscal year column in the dataset.

Capital Program

  • This project will address sidewalk gaps and poor sidewalk conditions by constructing/reconstructing sidewalk on south side of Burrstone Road (NYS 921B), west of French Road to Marauder Boulevard and on the north side of Burrstone Road from Washington Drive to French Road in the City of Utica, Town of New Hartford and Village of New York Mills. The beneficial outcomes of this project will include providing residents/pedestrians with a safe, contiguous, non-vehicular, ADA compliant connection to transit stops, healthcare facilities, restaurants, educational and religious institutions.
    PAVEMENT RECONSTRUCTION · Let by NYSDOT · Planned construction completion Mar 24, 2028
Source: NYSDOT Capital Program projects. Our copy checked Oct 31, 2026.

Structures named in the project title or its contracts

No structures.