Project

PIN 4LC105

Culvert Replacement/Rehab at Various Locations in Livingsto

Statewide Transportation Improvement Program programmed, not awarded

CULVERT REPLACEMENT/REHAB AT VARIOUS LOCATIONS IN LIVINGSTON, MONROE, AND WAYNE COUNTIES. CINS CA00240, C420086, C430032, C440072, C480006, C480009. THIS PROJECT COMPLIES WITH THE PROTECT FUNDING ELIGIBILITY MATRIX.

Programmed
FFY 2027: $14MTotal $14M in the listed years
Federal share
$8.6M
Agency
NYSDOT
Planning organization
GTC
Fund types
PROTECT, STATE
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Oct 31, 2026. FFY is the federal fiscal year column in the dataset.

Capital Program

  • Culvert replacement/rehab at various locations in Livingston, Monroe, and Wayne Counties.
    PAVEMENT RECONSTRUCTION · Let by NYSDOT · Planned construction completion Dec 31, 2030
Source: NYSDOT Capital Program projects. Our copy checked Oct 31, 2026.

Structures named in the project title or its contracts

No structures.