PIN 576543

TOWNLINE RD/ JOHNSON CRK; BIN 2213490

Statewide Transportation Improvement Program programmed, not awarded

TOWNLINE ROAD OVER JOHNSON CREEK BRIDGE REPLACEMENT, BIN 2213490; TOWN OF HARTLAND, NIAGARA COUNTY, BRIDGE NY 2023, BRIDGE FORMULA PROGRAM SHOWN AS 100% FEDERAL SHARE

Programmed
FFY 2026: $1.4MTotal $1.4M in the listed years
Federal share
$1.3M
Agency
HARTLAND TOWN
Planning organization
GBNRTC
County
Niagara
Fund types
BFP OFF SYS, LOCAL
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Oct 31, 2026. FFY is the federal fiscal year column in the dataset.

Structures named in the project title or its contracts

BINCarries / crossesCountyOwnerBuiltCondition
2213490
Bridge
TOWN LINE RD
over JOHNSON CREEK
NiagaraTown1966Poor