Project

PIN 582522

ESCALATOR REPLACEMENT - YEAR 6

Statewide Transportation Improvement Program programmed, not awarded

PROJECT WILL REPLACE LRRT STATION ESCALATORS. THE EXISTING ESCALATORS WILL BE REMOVED DOWN TO THE SUPPORT TRUSSES. THE TRUSSES WILL BE RE-USED TO SUPPORT THE NEW ESCALATOR. NEW MECHANICAL COMPONENTS, CONTROLLERS AND WIRING WILL ALL BE INSTALLED. THE NFTA WILL RETAIN ANY USABLE PARTS FROM THE REMOVED ESCALATORS FOR SPARE PARTS FOR THE REMAINING ESCALATORS OF THE SAME DESIGN. TOTAL PROJECT COST $2.10M

Programmed
FFY 2026: $2.1MTotal $2.1M in the listed years
Agency
NFTA
Planning organization
GBNRTC
County
Erie
Fund types
STATE
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Nov 1, 2026. FFY is the federal fiscal year column in the dataset.