Project
PIN 605640
NY 417 & NY 275 MBC PAVING, TOWN OF BOLIVAR
Statewide Transportation Improvement Program programmed, not awarded
PAVEMENT MILL AND FILL, SR 417 & SR 275, TO RESTORE TO STATE OF GOOD REPAIR, VILLAGE & TOWN OF BOLIVAR, ALLEGANY COUNTY.
- Programmed
- FFY 2027: $840k, FFY 2028: $5.8MTotal $6.6M in the listed years
- Federal share
- $4.0M
- Agency
- NYSDOT
- Planning organization
- RURAL
- County
- Allegany
- Fund types
- SDF, STBG FLEX
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Oct 31, 2026. FFY is the federal fiscal year column in the dataset.
Capital Program
- Pavement rehabilitation on NY 417 and NY 275 in the Village & Town of Bolivar, Allegany County.Corrective Maint · Let by NYSDOT · Planned construction completion Mar 19, 2029
Source: NYSDOT Capital Program projects. Our copy checked Oct 31, 2026.
Structures named in the project title or its contracts
No structures.