Statewide Transportation Improvement Program programmed, not awarded

THIS PROJECT WILL MAKE IMPROVEMENTS AT THE INTERSECTION OF FEDERAL-AID ELIGIBLE RT 3 (ARSENAL ST) AND BELLEW AVE TO IMPROVE THE FLOW OF TRAFFIC THROUGH THE INTERSECTION, WITH A PARTICULAR FOCUS ON IMPROVING CURB RADII FOR LARGE TRUCKS IN THE CITY OF WATERTOWN, JEFFERSON CO.

Programmed
FFY 2026: $366k, FFY 2028: $166k, FFY 2029: $2.2MTotal $2.8M in the listed years
Federal share
$2.2M
Agency
NYSDOT
Planning organization
WJCTC
County
Jefferson
Fund types
CRP MED URB, NHPP, SDF
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Oct 31, 2026. FFY is the federal fiscal year column in the dataset.

Capital Program

  • This project will make improvements at the intersections of Bellew Avenue and Arsenal Street (NY 3) to improve the flow of traffic through the intersection with a particular focus on large trucks in the City of Watertown, Jefferson County.
    SAFETY · Let by NYSDOT · Planned construction completion Mar 27, 2030
Source: NYSDOT Capital Program projects. Our copy checked Oct 31, 2026.

Structures named in the project title or its contracts