Project
PIN 7V2622
RT 11B, ST LAWRENCE CO LINE - DOUG SMITH RD (VPP)
Statewide Transportation Improvement Program programmed, not awarded
RESURFACE 3.3 MILES OF PAVEMENT ON RT 11B FROM ST. LAWRENCE CO LINE TO DOUG SMITH RD, TN OF DICKINSON, FRANKLIN CO.
- Programmed
- FFY 2026: $854kTotal $854k in the listed years
- Federal share
- $679k
- Agency
- NYSDOT
- Planning organization
- RURAL
- County
- Franklin
- Fund types
- SDF, STBG FLEX
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Oct 31, 2026. FFY is the federal fiscal year column in the dataset.
Capital Program
- This project will resurface 3.3 miles of RT 11B from St. Lawrence Co line to Doug Smith RD, in the Town of Dickenson, Franklin Co.Corrective Maint · Let by OGS · Planned construction completion Feb 26, 2027
Source: NYSDOT Capital Program projects. Our copy checked Oct 31, 2026.
Structures named in the project title or its contracts
No structures.