PIN 7VP009

RT 190, RM 1038 - ELLENBURG (VPP)

Statewide Transportation Improvement Program programmed, not awarded

RESURFACE 4.7 MILES OF PAVEMENT ON RT 190, FROM REFERENCE MARKER 1038 TO VIL OF ELLENBURG, TN OF ELLENBURG, CLINTON CO

Programmed
FFY 2026: $1.2MTotal $1.2M in the listed years
Federal share
$971k
Agency
NYSDOT
Planning organization
RURAL
County
Clinton
Fund types
SDF, STBG FLEX
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Oct 31, 2026. FFY is the federal fiscal year column in the dataset.

Capital Program

  • This project will resurface 4.7 miles of Route 190, from Sample Way to the Hamlet of Ellenburg in the Town of Ellenburg, Clinton County.
    Corrective Maint · Let by OGS · Planned construction completion Feb 26, 2027
Source: NYSDOT Capital Program projects. Our copy checked Oct 31, 2026.

Structures named in the project title or its contracts

No structures.