Project

PIN 7VP012

RT 30, VIL OF MALONE - CANADIAN BORDER (VPP)

Statewide Transportation Improvement Program programmed, not awarded

RESURFACE 10.4 MILES OF PAVEMENT ON RT 30, FROM VIL OF MALONE TO CANADIAN BORDER, TN OF MALONE & TN OF CONSTABLE, FRANKLIN CO

Programmed
FFY 2026: $2.3MTotal $2.3M in the listed years
Federal share
$1.8M
Agency
NYSDOT
Planning organization
RURAL
County
Franklin
Fund types
SDF, STBG FLEX
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Oct 31, 2026. FFY is the federal fiscal year column in the dataset.

Capital Program

  • This project will resurface 10.4 miles of Route 30, from the Village of Malone to the Canadian Border in the Towns of Malone & Constable, Franklin County.
    Corrective Maint · Let by OGS · Planned construction completion Feb 26, 2027
Source: NYSDOT Capital Program projects. Our copy checked Oct 31, 2026.

Structures named in the project title or its contracts

No structures.