Project

PIN 823951

ROUTE 9W AT OAK TREE ROAD INTERSECTION IMPROVEMENT

Statewide Transportation Improvement Program programmed, not awarded

ROUTE 9W AT OAK TREE ROAD INTERSECTION IMPROVEMENT. THIS PROJECT WILL REPLACE A TRAFFIC SIGNAL WITH A ROUNDABOUT TO MITIGATE CONGESTION AT THE INTERSECTION OF ROUTE 9W AT OAK TREE ROAD IN THE TOWN OF ORANGETOWN, ROCKLAND COUNTY. PEDESTRIAN FACILITIES WILL BE INSTALLED UP TO ADA STANDARDS WHERE FEASIBLE. NY797 (PROGRAM CODE: Y926).

Programmed
FFY 2026: $5.9MTotal $5.9M in the listed years
Federal share
$4.5M
Agency
NYSDOT
Planning organization
MHSTCC
County
Rockland
Fund types
HPP, SDF, STATE, STBG FLEX
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Oct 31, 2026. FFY is the federal fiscal year column in the dataset.

Capital Program

  • This project will replace a traffic signal with a roundabout to mitigate congestion at the intersection of Route 9W at Oak Tree Road in the Town of Orangetown, Rockland County. Pedestrian facilities will be installed up to Americans with Disabilities Act (ADA) standards where feasible including the introduction of new buffered sidewalks and crosswalks with pedestrian refuge islands.
    Renewal · Let by NYSDOT · Planned construction completion Dec 31, 2028
Source: NYSDOT Capital Program projects. Our copy checked Oct 31, 2026.

Structures named in the project title or its contracts

No structures.