Project

PIN 881759

WASHINGTON AVE CORRIDOR IMPRVMTS: SAWKILL RD TO SCHWENK DR

Statewide Transportation Improvement Program programmed, not awarded

PROJECT WILL MAKE OPERATIONAL AND SAFETY IMPROVEMENTS ALONG THE WASHINGTON AVENUE CORRIDOR FROM SAWKILL ROAD TO SCHWENK DRIVE, INCLUDING THE O&W RAIL TRAIL CROSSING. TOWN OF ULSTER AND CITY OF KINGSTON, ULSTER COUNTY.

Programmed
FFY 2027: $1.3M, FFY 2028: $20k, FFY 2029: $1.2MTotal $2.5M in the listed years
Federal share
$2.0M
Agency
NYSDOT
Planning organization
UCTC
County
Ulster
Fund types
NHPP, SDF
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Oct 31, 2026. FFY is the federal fiscal year column in the dataset.

Capital Program

  • This project will make safety and operational improvements along Washington Avenue from Schwenk Dr. to Sawkill Rd. The project will evaluate opportunities for improved pedestrian connectivity along Washington Avenue from RM 981K 8601 1000-2001 in the City of Kingston, Ulster County. Additionally, the project will investigate the existing signalized intersection of Sawkill Road and Washington Avenue in the Town of Ulster for improved traffic flow and safety.
    Renewal · Let by NYSDOT · Planned construction completion Dec 4, 2031
Source: NYSDOT Capital Program projects. Our copy checked Oct 31, 2026.

Structures named in the project title or its contracts