Project

PIN 935855

I88 RESURFACING, EXIT 2 TO 3 AND EXIT 5 TO CHENANGO CO LINE

Statewide Transportation Improvement Program programmed, not awarded

THIS CONTRACT RESURFACES I88 AND REPAIRS ISOLATED PAVEMENT AREAS FROM EXIT 2 TO 3 (MP 2.89 TO 3.22) AND FROM EXIT 5 TO THE CHENANGO COUNTY LINE (MP 12.96 TO 19.71) IN THE TOWNS OF FENTON AND COLESVILLE, BROOME COUNTY. THE RAMPS AT EXITS 3 AND 6 ARE INCLUDED IN THE PROJECT LIMITS. ADDITIONAL WORK INCLUDES NEW GUIDE RAIL/MEDIAN RAIL INSTALLATION, GROUND-MOUNTED SIGN STRUCTURE UPGRADES, AND NEW PAVEMENT MARKINGS. SAFETAP ITEMS ARE ALSO ADDRESSED AS RESOURCES ALLOW.

Programmed
FFY 2026: $200k, FFY 2027: $22MTotal $22M in the listed years
Federal share
$20M
Agency
NYSDOT
Planning organization
BMTS
County
Broome
Fund types
NHPP, SDF
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Oct 31, 2026. FFY is the federal fiscal year column in the dataset.

Capital Program

  • This contract resurfaces Interstate 88 and repairs isolated pavement areas from Exit 2 to 3 and from Exit 5 to the Chenango County line in the towns of Fenton and Colesville, Broome County. The ramps at exits 3 and 6 are included in the project limits. Additional work includes new guide rail/median rail installation, ground-mounted sign structure upgrades, and new pavement markings. Safety Appurtenance Program (SAFETAP) items are also addressed as resources allow.
    Corrective Maint · Let by NYSDOT · Planned construction completion Dec 2, 2027
Source: NYSDOT Capital Program projects. Our copy checked Oct 31, 2026.

Structures named in the project title or its contracts

No structures.