Project

PIN X05175

Safety and Mobility Improvements on Westbound GCP at Exit 10

Statewide Transportation Improvement Program programmed, not awarded

SAFETY AND MOBILITY IMPROVEMENTS ON WESTBOUND GRAND CENTRAL PARKWAY (STATE ROUTE 907M) EXIT 10 E-W AND GCP C-D ROAD TO LONG ISLAND EXPRESSWAY IN QUEENS COUNTY. THIS PROJECT WILL RECONFIGURE THE EXISTING EXIT RAMP FROM LIE WESTBOUND TO GCP WESTBOUND, PROVIDE AN ADDITIONAL TRAVEL LANE ON WB GCP EXIT 10 E-W C-D ROAD, AND ADDITIONAL DECELERATION LENGTH ON WB GCP MAINLINE. THE WORK WILL ALSO INCLUDE SHOULDER RECONSTRUCTION, SIGN PANELS, SIGN STRUCTURES, GUIDE RAIL AND CURB UPGRADES TO MEET CURRENT STANDARDS. OTHER UTILITY UPGRADES, SUCH AS DRAINAGE/ LIGHTING WILL ALSO BE INCLUDED. NYSDOT CERTIFIES THAT THIS PROJECT HAS BEEN APPROVED BY THE REGIONAL SAFETY EVALUATION ENGINEER AND SIGNED OFF BY THE REGIONAL TRAFFIC ENGINEER.

Programmed
FFY 2026: $580k, FFY 2028: $7.3MTotal $7.8M in the listed years
Federal share
$6.3M
Agency
NYSDOT
Planning organization
NYCTCC
County
Queens
Fund types
HSIP, SDF
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Nov 1, 2026. FFY is the federal fiscal year column in the dataset.

Capital Program

  • This project will address safety & mobility issues by reconfiguring Westbound Grand Central Parkway (State Route 907M) at Exit 10 E-W and GCP C-D Road to Long Island Expressway in Queens County, NYC. This project will also upgrade sign structures, sign panels, and guide rails.
    SAFETY · Let by NYSDOT · Planned construction completion Nov 6, 2028
Source: NYSDOT Capital Program projects. Our copy checked Nov 1, 2026.

Structures named in the project title or its contracts

No structures.