IMPLEMENTATION OF A PERMANENT CONCRETE BARRIER SYSTEM ALONG THE HENRY HUDSON PKWY MEDIAN AND SOUTHBOUND SHOULDER, AND OTHER ROADSIDE SAFETY IMPROVEMENTS. THE STATE CERTIFIES THAT THIS PROJECT HAS BEEN APPROVED BY THE REGIONAL SAFETY EVALUATION ENGINEER AND SIGNED OFF BY THE REGIONAL TRAFFIC ENGINEER. (RWDASP FUNDING 2025)

Programmed
FFY 2026: $936k, FFY 2027: $937k, FFY 2028: $52MTotal $54M in the listed years
Federal share
$3.1M
Agency
NYCDOT
Planning organization
NYCTCC
County
New York
Fund types
HSIP, LOCAL