Project
PIN X77470
BARRIER SYSTEM ALONG THE HUTCHINSON RIVER
Statewide Transportation Improvement Program programmed, not awarded
IMPLEMENTATION OF A PERMANENT CONCRETE BARRIER SYSTEM ALONG HUTCHINSON RIVER PARKWAY MEDIAN AND OTHER ROADSIDE SAFETY IMPROVEMENTS. THE STATE CERTIFIES THAT THIS PROJECT HAS BEEN APPROVED BY THE REGIONAL SAFETY EVALUATION ENGINEER AND SIGNED OFF BY THE REGIONAL TRAFFIC ENGINEER. (RWDASP FUNDING 2025)
- Programmed
- FFY 2026: $526k, FFY 2028: $5.9MTotal $6.4M in the listed years
- Federal share
- $4.4M
- Agency
- NYCDOT
- Planning organization
- NYCTCC
- County
- Bronx
- Fund types
- HSIP, LOCAL
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Nov 2, 2026. FFY is the federal fiscal year column in the dataset.