Project

PIN X77470

BARRIER SYSTEM ALONG THE HUTCHINSON RIVER

Statewide Transportation Improvement Program programmed, not awarded

IMPLEMENTATION OF A PERMANENT CONCRETE BARRIER SYSTEM ALONG HUTCHINSON RIVER PARKWAY MEDIAN AND OTHER ROADSIDE SAFETY IMPROVEMENTS. THE STATE CERTIFIES THAT THIS PROJECT HAS BEEN APPROVED BY THE REGIONAL SAFETY EVALUATION ENGINEER AND SIGNED OFF BY THE REGIONAL TRAFFIC ENGINEER. (RWDASP FUNDING 2025)

Programmed
FFY 2026: $526k, FFY 2028: $5.9MTotal $6.4M in the listed years
Federal share
$4.4M
Agency
NYCDOT
Planning organization
NYCTCC
County
Bronx
Fund types
HSIP, LOCAL
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Nov 2, 2026. FFY is the federal fiscal year column in the dataset.
PIN X77470 · BARRIER SYSTEM ALONG THE HUTCHINSON RIVER · NYSDOT Data