Project

PIN X80749

ITS Expansion Along CVE and GCP Phase 1

Statewide Transportation Improvement Program programmed, not awarded

EXPANSION OF THE INTELLIGENT TRANSPORTATION SYSTEM (ITS) NETWORK THROUGH MOST OF THE CLEARVIEW EXPRESSWAY (CVE) AND A SECTION OF GRAND CENTRAL PARKWAY (GCP) IN QUEENS COUNTY. THE PROJECT WILL ADD CLOSED-CIRCUIT TELEVISION CAMERAS, VARIABLE MESSAGE SIGNS, AND NEW GANTRIES. THERE WILL ALSO BE A NEW DEDICATED CONDUIT SYSTEM WITH FIBER OPTIC CABLE INSTALLED TO SUPPORT THESE ITS ELEMENTS. THE NEW ITS ELEMENTS WILL ENHANCE DATA SHARING CAPABILITIES, IMPROVE TRAFFIC MONITORING, AND FACILITATE COORDINATED RESPONSES TO INCIDENTS. OVERALL DESIGN AND PHASE 1 CONSTRUCTION OF SEGMENT ALONG THE GCP FROM KEW GARDENS INTERCHANGE TO CVE IS PROGRAMMED UNDER THIS PIN (X80749). PHASE 2 CONSTRUCTION OF THE SEGMENT ALONG THE CVE FROM CROSS ISLAND EXPRESSWAY TO GCP IS PROGRAMMED UNDER PIN X80754.

Programmed
FFY 2026: $3.1M, FFY 2027: $2.8M, FFY 2029: $40MTotal $45M in the listed years
Federal share
$36M
Agency
NYSDOT
Planning organization
NYCTCC
County
Queens
Fund types
CMAQ, SDF
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Nov 2, 2026. FFY is the federal fiscal year column in the dataset.

Capital Program

  • The proposed project will implement a Class A system which includes a new permanent conduit system for communication with a single mode fiber optic trunk cable for the entire length of each highway. The Class A system includes a full coverage communications network with a maximum incident detection time of five minutes. The proposed system will include twelve (12) new CCTV cameras, new IP traffic detectors, and four (4) new VMS gantries to serve both directions along the Clearview Expressway and the Grand Central Parkway. (Phase 1).
    OTHER · Let by NYSDOT · Planned construction completion May 1, 2030
Source: NYSDOT Capital Program projects. Our copy checked Nov 2, 2026.

Structures named in the project title or its contracts

No structures.