Projects
The Statewide Transportation Improvement Program: 2,489 entries by PIN, with Capital Program details on each project's page.
- PIN 901659STIPRT 12 OVER CHENANGO RIVER OVERFLOW, BRIDGE REPLACEMENTProgrammed FFY 2028 $1.0M, FFY 2029 $3.9M · Chenango
- PIN 901660STIPRT 12 JACK ARCH BRIDGE REPLACEMENT, TOWN OF SHERBURNEProgrammed FFY 2028 $1.0M · Chenango
- PIN 901917STIPRT 220 OVER RED BROOK, BRIDGE REPLACEMENTProgrammed FFY 2027 $1.0M, FFY 2028 $3.3M · Chenango
- PIN 902809STIPRT 23 OVER CANASAWACTA CREEKProgrammed FFY 2026 $5.0M · Chenango
- PIN 904259STIPRT 26 OVER GLENN BROOKProgrammed FFY 2029 $1.0M · Chenango
- PIN 905648STIPRT 8 SAFETY IMPROVEMENTSProgrammed FFY 2026 $938k, FFY 2027 $16M · Chenango
- PIN 905652STIPRT 12 LARGE CULVERT AND BRIDGE REPLACEMENT, TOWN OF NORTH NProgrammed FFY 2026 $5.5M · Chenango
- PIN 975510STIPCHENANGO COUNTY BRIDGE MAINTENANCE PROJECT (FFY 26)Programmed FFY 2026 $490k · Chenango
- PIN 975546STIPBLANDING RD OVER CHENANGO RIVER BRIDGE REPLACEMENT, BNY 22Programmed FFY 2026 $3.3M · Chenango
- PIN 975570STIPCHENANGO COUNTY BRIDGE MAINTENANCE PROJECT (FFY27)Programmed FFY 2027 $261k · Chenango
- PIN 975571STIPCHENANGO COUNTY BRIDGE MAINTENANCE PROJECT (FFY28)Programmed FFY 2028 $261k · Chenango
- PIN 975572STIPCHENANGO COUNTY BRIDGE MAINTENANCE PROJECT (FFY29)Programmed FFY 2029 $261k · Chenango
- PIN 975584STIPWHITE STORE RD OVER TRIB WHITE STORE BK BRIDGE REPLACE BNY23Programmed FFY 2026 $161k, FFY 2027 $1.8M · Chenango
- PIN 980757STIPINTERSTATE 81, 88 AND RT 17 MEDIAN BARRIER BLOCKProgrammed FFY 2028 $1.5M, FFY 2029 $1.5M · Broome
- PIN 980774STIPBRIDGE RAIL REPLACEMENT, REGIONWIDE, SFY 2025Programmed FFY 2026 $2.3M · Broome
- PIN 980775STIPSCOUR PROJECT 2027Programmed FFY 2027 $2.3M · Broome
- PIN 9ADA22STIPADA ACCESSIBILITY PROJECT: REGION 9Programmed FFY 2027 $1.7M · Chenango
- PIN 9ADA24STIPADA ACCESSIBILITY PROJECTProgrammed FFY 2027 $1.2M · Broome
- PIN 9ADA28STIPADA ACCESSIBILITY PROJECT FFY28Programmed FFY 2028 $173k, FFY 2029 $2.8M · Broome
- PIN 9CRS27STIPCLEANING AND SEALING CRACKS REGIONWIDE, 2027Programmed FFY 2026 $1k, FFY 2027 $943k · Broome
- PIN 9CRS65STIP2026 CRACK SEALING, REGIONWIDEProgrammed FFY 2026 $818k · Broome
- PIN 9CWS01STIPCURVE WARNING SIGN UPGRADES, REGION 9Programmed FFY 2026 $7.2M · Broome
- PIN 9FAS24STIPF.A. SIGNAL REQUIREMENTS CONTRACT FFY24Programmed FFY 2026 $5.0M · Broome
- PIN 9FAS28STIPF.A. SIGNAL REQUIREMENTS CONTRACT FFY28Programmed FFY 2027 $130k, FFY 2028 $2.9M · Broome
- PIN 9FAS30STIP9FAS28 - F.A. SIGNAL REQUIREMENTS CONTRACT FFY30Programmed FFY 2027 $515k, FFY 2029 $230k · Broome
1–25 of 68
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Oct 31, 2026. Programmed amounts are plans, not awards. Download these as CSV