Projects

The Statewide Transportation Improvement Program: 2,489 entries by PIN, with Capital Program details on each project's page.

  • RT. 167: DOLGEVILLE W. VIL. LN. TO RT. 29, VILLAGE OF DOLGE
    Programmed FFY 2026 $500k, FFY 2028 $2.5M · Herkimer
  • RT 167: RT 5 TO DOLGEVILLE VIL LN PAVING PROJECT, HERKIMER C
    Programmed FFY 2026 $5.0M · Herkimer
  • PAVEMENT IMPROVEMENT PROJECT - ROUTE 20 - ONEIDA COUNTY
    Programmed FFY 2026 $6.4M · Herkimer
  • RT. 5/E. CANADA CREEK (BIN 1002460) BRIDGE REPLACEMENT
    Programmed FFY 2026 $12M · Herkimer
  • RT. 5/DYKE RD. INTERSECTION IMP PROJECT, TOWN OF SCHUYLER
    Programmed FFY 2026 $1.2M, FFY 2027 $1.8M · Herkimer
  • RT. 29 OVER E. CANADA CRK, (BIN 1051170) HERKIMER/FULTON CO.
    Programmed FFY 2026 $2.9M, FFY 2027 $22M · Fulton
  • BNY 2021: HARVEY BRIDGE RD OVER W. CANADA CK (BIN 2204740)
    Programmed FFY 2026 $299k, FFY 2027 $3.6M · Herkimer
  • BRIDGE NY 2022: RAILROAD ST. OVER CSX/AMTRAK (BIN 4423040)
    Programmed FFY 2026 $2.5M · Herkimer
  • PECKVILLE RD/GILLETTE CRK (BIN 3307770), T/O MANHEIM
    Programmed FFY 2026 $2.2M · Herkimer
  • BRIDGE NY 2023: PINEBUSH RD/TRIB TO FULMER CRK (BIN 2272000)
    Programmed FFY 2026 $132k, FFY 2027 $1.5M · Herkimer
  • BRIDGE NY 2023: DYKE RD & BLEECKER ST EXT/FERGUSON CRK & BLE
    Programmed FFY 2026 $172k, FFY 2027 $1.6M · Herkimer
  • BRIDGE NY 2023: SHELLS BUSH RD/WEST CANADA CRK (BIN 2204620)
    Programmed FFY 2026 $108k, FFY 2027 $677k · Herkimer
  • RWDSAP 25: HERKIMER COUNTY ROADSIDE SAFETY ENHANCEMENTS
    Programmed FFY 2026 $1.3M · Herkimer
  • ROADSIDE SAFETY/GUIDERAIL PROJECT 27
    Programmed FFY 2027 $206k, FFY 2028 $3.1M · Fulton
  • PAVEMENT MARKING PROJECT 26
    Programmed FFY 2026 $5.2M · Fulton
  • CULVERT REPAIR / REPLACEMENT PROJECT 25
    Programmed FFY 2026 $3.6M · Fulton
  • CULVERT REPAIR / REPLACEMENT PROJECT 27
    Programmed FFY 2026 $619k, FFY 2027 $2.5M · Fulton
  • BRIDGE PAINTING PROJECT 27
    Programmed FFY 2026 $5.0M · Fulton
  • TRAFFIC SYSTEMS IMPROVEMENT PROJECT 26
    Programmed FFY 2026 $361k, FFY 2027 $2.6M · Fulton
  • INTERSECTION IMPROVEMENT PROJECT 27
    Programmed FFY 2026 $70k, FFY 2027 $111k, FFY 2028 $914k · Fulton
  • 280698 - BRIDGE CLEANING PROJECT 26
    Programmed FFY 2026 $770k · Fulton
  • HIGBY RD./RT. 5S BR REPLACEMENT, T/O FRANKFORT, HERKIMER CO.
    Programmed FFY 2027 $6.2M · Herkimer
  • ROADSIDE SAFETY/GUIDERAIL PROJECT 28
    Programmed FFY 2026 $103k, FFY 2027 $75k, FFY 2028 $1.9M · Fulton
  • ROADSIDE SAFETY/GUIDERAIL PROJECT 29
    Programmed FFY 2027 $103k, FFY 2028 $75k, FFY 2029 $1.9M · Fulton
  • ROADSIDE SAFETY/GUIDERAIL PROJECT 30
    Programmed FFY 2028 $103k, FFY 2029 $75k · Fulton
1–25 of 67