Projects
The Statewide Transportation Improvement Program: 2,489 entries by PIN, with Capital Program details on each project's page.
- PIN 304370STIPSAFETY IMPROVEMENTS, RT 11, I-81 OFF RAMP TO RT 11A, ONON COProgrammed FFY 2026 $50k, FFY 2028 $362k · Onondaga
- PIN 328723STIPSAFETY IMPROVEMENTS, ONONDAGA LAKE PKWY , TN SALINA, ONON COProgrammed FFY 2027 $723k, FFY 2029 $27M · Onondaga
- PIN 350181STIPI81 OVER RIDGE RD BRIDGE REPLACEMENTS, TOWN OF CORTLANDVILLProgrammed FFY 2027 $1.4M, FFY 2029 $28M · Cortland
- PIN 350186STIPBRIDGE REPLACEMENT, I-81, OVER ROUTE 11, NEDROW, ONON COProgrammed FFY 2026 $30M · Onondaga
- PIN 350186STIPBRIDGE REHAB, I-81, OVER ROUTE 11, NEDROW, ONON COProgrammed FFY 2026 $29M · Onondaga
- PIN 350188STIPBRIDGE REHAB, HIAWATHA BLVD, OVER I-81, SYR, ONON COProgrammed FFY 2028 $864k · Onondaga
- PIN 350195STIPI-81 VIADUCT - REBUILD I-690 & WEST STREET INTERCHANGEProgrammed FFY 2026 $1014M · Onondaga
- PIN 350196STIPBUSINESS LOOP 81, NORTHERN SECTION, PH. 2, SYRACUSE, ONON COProgrammed FFY 2027 $344M · Onondaga
- PIN 350197STIPBUSINESS LOOP 81, SOUTHERN SECTION, PH. 2, SYRACUSE, ONON COProgrammed FFY 2027 $374M · Onondaga
- PIN 350198STIPSUPPORT SERVICES, I-81 COMMUNITY GRID, ONONDAGA COProgrammed FFY 2026 $5.2M · Onondaga
- PIN 350199STIPBRIDGE REHAB, I-81, OVER ONEIDA RIVER/BARGE CANAL, ONON/OSWProgrammed FFY 2027 $530k, FFY 2028 $54M · Oswego
- PIN 350201STIPMBC I-81, BROOME CO LINE TO RT 41, CORTLAND COUNTYProgrammed FFY 2026 $86M · Cortland
- PIN 350202STIPBRIDGE REHAB, I81 OVER ONEIDA RIVER PH 2 SB BRIDGE, ONON/OSWProgrammed FFY 2027 $530k · Oswego
- PIN 350203STIPMBC I-81 RM 3038 TO 3087, MILL TRAVEL LANES, CORTLANDProgrammed FFY 2026 $1.2M, FFY 2027 $600k, FFY 2028 $7.1M · Cortland
- PIN 350204STIPI-81 VIADUCT - I-690 AND BL 81 DRAINAGE TRUNK LINEProgrammed FFY 2026 $114M · Onondaga
- PIN 375769STIPRECONNECT, COMPLETE ST GRID, E ADAMS/15TH WARD, SYR, ONON COProgrammed FFY 2026 $29M · Onondaga
- PIN 395070STIPNORTHEAST GATEWAY INTERMODAL CORRIDOR, CITY OF CORTLANDProgrammed FFY 2028 $7.7M · Cortland
- PIN 701669STIPRT 12 @ I-81 EXIT 47Programmed FFY 2026 $500k, FFY 2027 $260k · Jefferson
- PIN 703311STIPRT 342 / I81Programmed FFY 2026 $1.3M, FFY 2027 $25M · Jefferson
- PIN 7V2563STIPRT 970K, RT 232 - I-81 SB RAMP (VPP)Programmed FFY 2028 $95k · Jefferson
- PIN 7V2631STIPI-81, PERCH LAKE - RT 411 (VPP)Programmed FFY 2026 $2.4M · Jefferson
- PIN 7V2964STIPRT 342, RT 12 - I-81 (VPP)Programmed FFY 2029 $304k · Jefferson
- PIN 7VP003STIPI-781, I-81 INTERCHANGE - FORT DRUM (VPP)Programmed FFY 2026 $3.6M · Jefferson
- PIN 7VP007STIPRT 232 & 970K, I-81 - RT 11 (VPP)Programmed FFY 2026 $792k · Jefferson
- PIN 950129STIPI81 RESURFACING, EXIT 13B(OLD EXIT 5) TO EXIT 21(OLD EXIT 7)Programmed FFY 2026 $22M · Broome
1–25 of 31
Source: Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Nov 2, 2026. Programmed amounts are plans, not awards. Download these as CSV