Contract

D265262

DRAINAGE, MEDIAN BARRIER & WALL IMPROVEMENTS - Route 9W, Towns of Cornwall & Highlands, Village of Cornwall-On-Hudson. C840005, C840010, C840075

Download CSV

Record-plan index

Award date
Aug 27, 2024
Route
US 9W
County
Orange
NYSDOT region
8 Poughkeepsie
Sheets indexed
55As-built scanned: No · As-let: Yes
Source: NYSDOT Highway Record Plans, updated Jun 26, 2026. Our copy checked Oct 31, 2026. Scan flags are index metadata, not a file listing: files can exist when they say no, and the reverse.

Program listings matched by contract number or PIN

  • PIN 881355Capital ProgramNames this contract
    This project will replace the parapet wall and improve the super elevation along the northbound lane of US Route 9W in the Town of Highlands. The roadway will also be resurfaced in both directions surrounding the parapet wall. This project will also include improvements to drainage including underdrain installation and reestablishing asphalt gutters at sufficient depths and replacement of median concrete barriers along 9W on Storm King Mountain in the Towns of Cornwall and Highlands and Village of Cornwall-on-Hudson in Orange County.
    OTHER · Contract D265262 · Planned completion Jul 19, 2026
Source: NYSDOT Capital Program projects; Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Oct 31, 2026.

Structures named 2 found in the structure layers

BINCarries / crossesCountyOwnerBuiltCondition
1007199
Bridge
US9W
over 218 218 83011033
OrangeNYSDOT1940Fair
1007209
Bridge
US9W
over BLACK FOREST CREEK
OrangeNYSDOT1937Good
Source: NYSDOT Bridges; NYSDOT Large Culverts. Our copy checked Oct 31, 2026. From the BINs in the index row and in program titles. Verify which drawings apply to your structure.