Contract

D265810

This project micromills the existing Novachip overlay, repairs concrete slabs and installs a new asphalt top course along Route 201. Additional work includes the installation of new guide railing/median barrier, new signs, curb ramps and pavement markings. Village of Johnson City, Town of Union, Broome County.

Capital Program

Route
Not recorded
County
Not recorded

This contract is not in the record-plan index yet (the index lags recent work). It is named by a Capital Program project below.

Source: NYSDOT Capital Program projects. Our copy checked Nov 2, 2026. Scan flags are index metadata, not a file listing: files can exist when they say no, and the reverse.

Program listings matched by contract number or PIN

  • PIN 904508Capital ProgramNames this contract
    This project micromills the existing Novachip overlay, repairs concrete slabs and installs a new asphalt top course along Route 201. Additional work includes the installation of new guide railing/median barrier, new signs, curb ramps and pavement markings. Village of Johnson City, Town of Union, Broome County.
    Corrective Maint · Contract D265810 · Planned completion Mar 13, 2027
  • PIN 904508STIPSame PIN
    RT 201 RESURFACING, FLYOVER TO HARRY L DRIVE
    Programmed FFY 2026 $6.0M · Broome
  • PIN 904508STIPSame PIN
    RT 201 RESURFACING, FLYOVER TO HARRY L DRIVE
    Programmed FFY 2026 $8.2M · Broome
Source: NYSDOT Capital Program projects; Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Nov 2, 2026.

Structures named 0 found in the structure layers

No structures.

Source: NYSDOT Bridges; NYSDOT Large Culverts. Our copy checked Nov 2, 2026. From the BINs in the index row and in program titles. Verify which drawings apply to your structure.