This milling and resurfacing project will restore a smooth riding surface to the 14.59 mile portion of I-81 from the Broome County line to Route 41, in the Cortland County Towns of Marathon, Lapeer, Virgil and Cortlandville, and the Village of Marathon. Traffic will be maintained on-site using daily lane closures

Capital Program

Route
Not recorded
County
Not recorded

This contract is not in the record-plan index yet (the index lags recent work). It is named by a Capital Program project below.

Source: NYSDOT Capital Program projects. Our copy checked Nov 1, 2026. Scan flags are index metadata, not a file listing: files can exist when they say no, and the reverse.

Program listings matched by contract number or PIN

  • PIN 350201Capital ProgramNames this contract
    This milling and resurfacing project will restore a smooth riding surface to the 14.59 mile portion of I-81 from the Broome County line to Route 41, in the Cortland County Towns of Marathon, Lapeer, Virgil and Cortlandville, and the Village of Marathon. Traffic will be maintained on-site using daily lane closures
    Renewal · Contract D265835 · Planned completion Mar 3, 2029
  • PIN 350201STIPSame PIN
    MBC I-81, BROOME CO LINE TO RT 41, CORTLAND COUNTY
    Programmed FFY 2026 $86M · Cortland
Source: NYSDOT Capital Program projects; Statewide Transportation Improvement Program (STIP), updated Jun 23, 2026. Our copy checked Nov 1, 2026.

Structures named 0 found in the structure layers